165 MW Power Generation Plant

Project Name:165 MW Power Generation Plant

Client:Aggreko Middle East Limited FZE

Start Date:Nov 2020

End Date:July 2021

Alternate Text

Description of Project:

Supply and construction of cooling water system, fire fighting system, gas pipe work and skids, fire and gas system for 165 MW power station serve in Kalar Oilfield. 

Details of the work:

- Assembly of firefighting tanks (350 m3), installation of firefighting pumps (Diesel with electrical and jokey pump). including foundation of pumps and shade.

- Supply and installation of all firefighting pipes with supports (Including foam skids) with sand blasting and painting.

- Sludge catcher piping and piping work (Gas pipe, drain, and vent) for sludge catcher area.

- Gas platform piping and piping work for after sludge catcher area to the generators (12”, 8”,6",4”) nearly 1800 m.l including sand blasting painting, insulation and cladding for all pipes.

Alternate Text

Our Partners

Alternate Text
AGRU PIPE
FLOWORK
Klinger Gaskets
CPS Generators
US PIPE
DAB Pumps
TSI Limited
VAG
IKConseng
FGWilson
LucyElectric
Brush

Voltec Engineering’s multidisciplinary approach represents one focal point with an expert team to cover all your professional needs. For more information about us, please download our company profile